Diesel generator sets are everywhere in Delhi NCR: in housing societies, office towers, malls, hospitals, hotels, data centres, factories and construction sites. They are also a significant source of winter air pollution, and so they are closely regulated. National emission norms under the Environment (Protection) Rules apply to every genset sold in India, with the CPCB IV+ norms for new gensets up to 800 kW. In NCR, the Commission for Air Quality Management has added directions that limit when gensets can be used and require larger ones to be converted to dual fuel or fitted with approved retrofit devices. And under the Graded Response Action Plan, as revised on 28 September 2026, actions on DG sets now begin at Stage I.
This guide explains the rules in plain words, the options for bringing a genset into compliance, what housing societies and buildings need to do, and how to handle inspections and notices. For the full service page, see DG set emission norms.
हिंदी में सारांश
दिल्ली NCR में हाउसिंग सोसाइटी, ऑफ़िस, मॉल, अस्पताल, होटल, डेटा सेंटर और फ़ैक्ट्रियों में डीज़ल जनरेटर (DG सेट) आम हैं। नए जनसेट पर CPCB IV+ मानक लागू हैं। NCR में CAQM के निर्देश इनके इस्तेमाल को सीमित करते हैं और बड़े जनसेट को ड्यूल फ़्यूल या अनुमोदित रेट्रोफ़िट उपकरण से लैस करना ज़रूरी करते हैं। 28 सितंबर 2026 के GRAP संशोधन के बाद DG सेट की पाबंदियाँ स्टेज I से ही शुरू हो जाती हैं। सर्दी से पहले तैयारी करें।
The rules at a glance
National norms
CPCB IV+ norms for new gensets up to 800 kW, with type approval.
CAQM directions
Limit use in NCR and require upgrades for larger gensets.
Upgrade options
Dual fuel conversion, approved retrofit device, or replacement.
GRAP
DG set actions from Stage I after the 2026 revision.
Who is checked
Societies, offices, malls, hospitals, factories and sites.
Paperwork
Certificates and logbooks matter as much as hardware.
The national emission norms
Gensets sold in India must be type approved and meet emission limits set under the Environment (Protection) Rules. For new diesel gensets up to 800 kW, the CPCB IV+ norms apply, significantly reducing particulate and nitrogen oxide emissions compared with earlier norms. Each genset should carry a type approval certificate and conformity label, and must be installed with a stack of the required height and an acoustic enclosure meeting noise limits. Older gensets built to earlier norms can continue to be used where the law and local directions allow, but in NCR they face the additional CAQM requirements.
CAQM directions in NCR
The Commission for Air Quality Management has issued directions across NCR that, in broad terms, restrict the use of diesel gensets to emergencies and essential services, and require gensets above specified capacity bands that are used to be converted to dual fuel, running mainly on gas, or fitted with approved retrofit emission control devices that cut particulate emissions, within timelines the Commission has set. Smaller gensets and those in essential services have had different treatment. The directions have been revised several times, so the exact requirement for your genset depends on its capacity, use and the current direction.
Because GRAP DG set actions now begin at Stage I, restrictions that used to apply only when air quality became very poor now apply from the start of the winter season. Buildings should plan compliant backup power before October.
How to make your gensets compliant
List every genset
Rating, age, norm, location and use.
Check the current direction
Which capacity bands need conversion or retrofit.
Choose a route
Dual fuel, retrofit device, replacement or alternative backup.
Use approved suppliers
For conversion kits and retrofit devices.
Collect certificates
Type approval, conversion and retrofit test certificates.
Keep a logbook
Running hours and reasons for use.
Options compared
| Option | When it suits | Points to check |
|---|---|---|
| Dual fuel conversion | Larger gensets where piped gas is available | Gas connection, conversion certificate, gas share |
| Retrofit emission control device | Gensets that must stay on diesel | Approved device, test certificate, maintenance |
| Replacement with CPCB IV+ genset | Old gensets near end of life | Type approval, stack and enclosure |
| Battery or grid backup | Low-load needs and short outages | Capacity, fire safety, cost |
Housing societies and buildings
In a housing society, the maintenance agency or the residents' welfare association is usually treated as responsible for the gensets, and receives the notice. In office buildings and malls, the owner or facility manager is responsible, though tenants with their own gensets have their own duties. Hospitals and data centres, which need continuous power, may fall within essential service provisions, but must still use compliant gensets. Agreements with maintenance agencies should require compliance with CAQM directions, so that responsibilities are clear.
Inspections and notices
During winter drives, inspection teams check gensets for conformity labels, conversion or retrofit certificates, stack height, enclosures and logbooks. A genset that has been upgraded but cannot be shown to be compliant on paper is often treated as non-compliant. If you receive a notice or a sealing direction, gather the certificates and logbooks, explain the use, for example during a power failure, and apply for revocation with evidence. If a genset is not yet compliant, show the purchase order or work order for conversion and seek time. See closure notice reply.
A society prepared before winter
Here's a made-up example. A Gurugram housing society had two 500 kVA diesel gensets and expected restrictions in winter.
In August, it converted both gensets to dual fuel through an approved supplier, obtained certificates, and put in place a logbook. When inspectors visited in November, the society produced the documents, and no action was taken.
Running hours and permitted use
CAQM directions generally allow gensets to be used for emergencies and essential services, not as a routine substitute for grid power. In practice, this means gensets in buildings and factories should run only during power failures, and the running hours should be recorded. A logbook showing date, start and stop times, load, fuel used and the reason for running is the simplest way to prove permitted use. Inspection teams in NCR often ask for it. Gensets that run for long hours every day in an area with reliable grid supply attract suspicion even if they are upgraded.
Essential services, such as hospitals, life-saving equipment, telecom towers, data centres and lifts in high-rise buildings, have been treated differently under the directions, but they must still use compliant gensets and keep records. Where a building relies on gensets because its grid connection is inadequate, applying for an enhanced connection or adding battery storage is often the long-term solution.
Costs and choices
The right route depends on numbers. Dual fuel conversion costs vary with genset size and require a piped gas connection, but reduce diesel use and emissions. Retrofit emission control devices are installed on the exhaust and require maintenance, such as periodic cleaning or regeneration. Replacement with a new CPCB IV+ genset is a larger capital cost but may suit old gensets near the end of their life. Battery storage can handle short outages and low loads without any emissions. For many buildings, a mix works best: battery storage for short outages and lighting, and an upgraded genset for longer failures.
Whatever route you choose, use suppliers whose kits or devices are approved under the CAQM directions, and insist on certificates. A cheaper, unapproved device may not be accepted at inspection, leaving you exposed.
Documents inspection teams ask for
| Document | What it shows |
|---|---|
| Type approval and conformity certificate | The genset meets the emission norm for its rating |
| Dual fuel conversion certificate | The genset was converted by an approved supplier |
| Retrofit device test certificate | The device is approved and fitted to that genset |
| Stack height and enclosure details | Installation meets the norms |
| Running hours logbook | Use is limited to permitted purposes |
| Fuel and gas bills | Fuel actually used |
Before the winter season
- Have all gensets been listed with rating, age and norm?
- Do larger gensets have conversion or retrofit certificates?
- Is a logbook maintained for each genset?
- Has the maintenance agency's contract been updated for CAQM compliance?
- Is there a plan for backup power if gensets are restricted under GRAP?
- Are certificates kept where inspectors can see them quickly?
Frequently Asked Questions
Are diesel gensets banned in Delhi NCR?
Not outright, but their use is restricted and larger ones must be upgraded under CAQM directions.
What are CPCB IV+ norms?
Emission norms for new diesel gensets up to 800 kW.
What is a dual fuel kit?
A conversion that lets a genset run mainly on gas with some diesel.
What is a retrofit device?
An approved emission control device fitted to cut particulate emissions.
When do GRAP genset restrictions start?
From Stage I after the September 2026 revision.
Who is responsible in a housing society?
Usually the maintenance agency or RWA.
Do hospitals get exemptions?
Essential services have different treatment but must use compliant gensets.
What documents should I keep?
Type approval, conversion or retrofit certificates, and logbooks.
Can a genset be sealed?
Yes, non-compliant gensets can be sealed during drives.
Can sealing be revoked?
Yes, on showing compliance.
Gensets to Bring Into Line?
Send us your genset list. We will tell you what the current directions require.
This page gives general information about environmental law as it stood when it was last reviewed. It is not legal advice on your case and does not promise any result. Environmental rules, EPR targets, GRAP measures and board procedures change often, so check the current position for your unit or project before acting.