Environmental Clearance Before Starting Your Project

Does your project need environmental clearance? Category A and B, screening, scoping, public hearing, appraisal on PARIVESH, compliance.

Advice and representation before the pollution boards, environment authorities and the National Green Tribunal, for industries, builders, hospitals, RWAs and residents, led by Advocate BK Singh.

Get A Free Consultation

Last reviewed: October 2026

Some projects cannot start at all, not even site preparation, until they receive prior environmental clearance under the Environment Impact Assessment Notification, 2006. The notification lists the projects and activities that need EC: mining, thermal power, river valley projects, many industries such as cement, metals, chemicals and pharmaceuticals, infrastructure like highways, ports and airports, and large building and township projects. Category A projects are appraised by the Union Ministry of Environment, Forest and Climate Change; Category B projects by the State Environment Impact Assessment Authority.

EC is a demanding process with studies, public consultation for many projects, and appraisal by expert committees, followed by conditions that last for the life of the project. The Supreme Court, in its July 2026 decision in Vanashakti v Union of India, reaffirmed that prior EC is mandatory and ended the open-ended route for post-facto clearance under a 2021 office memorandum. This page explains who needs EC, how the process works, how long it takes and what happens after clearance.

What it isPrior approval for listed projects before any construction or expansion
Who grantsMoEFCC (Category A) or the State Environment Impact Assessment Authority (Category B)
PortalPARIVESH
Latest lawPrior EC is mandatory

हिंदी में सारांश

खनन, ऊर्जा, सीमेंट, रसायन, हाईवे, बंदरगाह और बड़े बिल्डिंग प्रोजेक्ट जैसे सूचीबद्ध प्रोजेक्ट शुरू करने से पहले EIA अधिसूचना, 2006 के तहत पर्यावरण मंज़ूरी (EC) ज़रूरी है। कैटेगरी A के लिए पर्यावरण मंत्रालय और कैटेगरी B के लिए राज्य स्तरीय प्राधिकरण (SEIAA) मंज़ूरी देते हैं; आवेदन PARIVESH पोर्टल पर होता है। सुप्रीम कोर्ट ने जुलाई 2026 में दोहराया कि पहले से EC अनिवार्य है।

Check first

Is this your situation?

  • You are planning a mine, industrial project or infrastructure project
  • Your building or township project has a large built-up area
  • You want to expand an existing project that holds EC
  • You have started work and are unsure whether EC was needed
  • Your EC application is stuck at screening, scoping or appraisal
  • You have received a show-cause notice for violating EC conditions
  • You are buying a project and want to check its EC status
Key facts

EC at a glance

Category A

Appraised by an Expert Appraisal Committee and decided by MoEFCC.

Category B

Appraised by the State Expert Appraisal Committee and decided by the SEIAA; B1 projects need an EIA report and usually a public hearing, B2 projects do not.

Four stages

Screening (for B projects), scoping (terms of reference), public consultation and appraisal.

PARIVESH

Applications, documents and decisions are handled online on the PARIVESH portal.

Integration with CTE

Since November 2024, units with EC do not need a separate Consent to Establish from the pollution board.

After clearance

Conditions must be followed for the life of the project, with six-monthly compliance reports.

Step by step

How the EC process works

1

Check applicability

Find your project in the Schedule to the EIA Notification and confirm the category and thresholds.

2

Screening

For Category B projects, the SEAC decides whether the project is B1 or B2.

3

Scoping

The appraisal committee sets terms of reference for the EIA study. Standard terms of reference apply to many sectors.

4

EIA study and public consultation

An accredited consultant prepares the EIA report; a public hearing is held by the pollution board for projects that need it, and written comments are invited.

5

Appraisal

The committee examines the final EIA report, public hearing outcomes and replies, and recommends grant or rejection.

6

Decision and conditions

The regulatory authority grants or refuses EC, with specific and general conditions.

Current law

The Vanashakti rulings and post-facto clearance

For years, projects that started without EC sought clearance after the event through a 2017 notification and a 2021 office memorandum. In May 2025, a two-judge bench of the Supreme Court struck these down; in November 2025, a three-judge bench recalled that decision; and on 29 July 2026, the three-judge bench delivered its final decision. It held that prior EC under the 2006 Notification is mandatory; upheld the 2017 notification, which gave violators a one-time six-month window, as a narrow and time-bound exception; and quashed the 2021 office memorandum, with prospective effect. Clearances already granted under it remain unless individually challenged, but fresh applications under the 2021 route are barred.

The practical message is plain: no work should start on a project listed in the Schedule before EC is granted. For projects already in violation, the options are now very limited and need careful legal advice.

Keeping EC valid

After clearance: conditions and compliance

EC comes with conditions on pollution control, green belt, water use, waste, monitoring and community measures. The project must file six-monthly compliance reports, and the regional office of MoEFCC or the state authority can inspect. Breach of conditions can lead to directions under Section 5 of the Environment (Protection) Act, penalties after the Jan Vishwas amendments, and in serious cases suspension or revocation. EC also has a validity period, set by the notification for different types of projects, within which construction or operations must begin. See EC compliance reports.

What to expect

Time and typical cost

Our fees are agreed in writing at the start, stage by stage. They are not linked to the outcome.

StageUsual timeWhat it involves
Applicability check1 to 2 weeksOur fee
Scoping and terms of reference1 to 3 monthsConsultant's fee
EIA study (B1 and A)Often one season of baseline data plus analysisConsultant's fee
Public hearingAs scheduled by the pollution boardNotices, hearing
Appraisal and decisionMonths, depending on committee meetingsPresentations, replies
Paperwork

Documents usually needed

Project

  • Pre-feasibility report and project layout
  • Land documents and land use permissions

Studies

  • EIA and environmental management plan (for B1 and A)
  • Baseline data and modelling

Other approvals

  • Forest and wildlife clearance status, if applicable
  • Groundwater and water supply arrangements

Public consultation

  • Public hearing proceedings and replies to issues raised
Legal basis

Laws that apply

Environment (Protection) Act, 1986

The parent law under which the EIA Notification is issued.

EIA Notification, 2006

List of projects requiring prior EC, categories and procedure.

MoEFCC notifications of November 2024

Integration of EC and CTE.

Vanashakti v Union of India (29 July 2026)

Prior EC mandatory; 2017 window upheld; 2021 office memorandum quashed prospectively.

Our approach

How we work

We are a litigation and advisory practice led by Advocate BK Singh, with offices in Dwarka (New Delhi) and Vaishali (Ghaziabad). This is what you can expect:

  • Applicability settled first: thresholds and category checked against the Schedule.
  • Legal oversight of the process: with your EIA consultant.
  • Public hearing preparation: issues anticipated and answered.
  • Conditions reviewed: before you accept them.
  • Written fee terms: agreed stage by stage, never linked to the outcome.
Avoid these

Mistakes we see with EC

  • Starting site work before EC
  • Splitting a project to stay under thresholds
  • Ignoring forest or wildlife approvals needed alongside EC
  • Treating EC conditions as a formality
  • Missing six-monthly compliance reports
Illustration

An industrial project in Haryana

Here's a made-up example. A company planned a chemical manufacturing project in a Haryana industrial estate. It had bought land and wanted to start foundations while studies were completed.

We advised that the project was listed in the Schedule and needed prior EC, and that no construction could begin. The EIA study and public hearing were completed, and the SEIAA granted EC with conditions on effluent treatment and green belt. Because the company held EC, it did not need a separate CTE, and moved directly to construction.

Illustration

A project that started too early

Here's a second made-up example. A developer had started excavation for a project that needed EC, believing it could apply under the 2021 post-facto route. After the July 2026 decision, that route was no longer available for fresh applications.

We advised stopping work at once, assessing the environmental impact of what had been done, and engaging with the authority on the legal position. The developer's exposure to penalties and compensation depended on the extent of work done and its impact, and the project timeline was significantly delayed.

What to expect

The public hearing

For Category A projects and Category B1 projects, other than those exempted, the EIA process includes public consultation. The public hearing is conducted by the state pollution control board with the district administration at or near the project site. Notice must be published in newspapers, including one in the local language, giving at least thirty days for the public to attend and respond, and the draft EIA report and summary must be made available. The proceedings are recorded and video-graphed, and the minutes are sent to the appraising authority.

Project proponents sometimes treat the hearing as a formality. That is a mistake. Issues raised by villagers, residents and organisations at the hearing must be addressed in the final EIA report, and courts and the NGT have set aside clearances where the hearing was not properly conducted or concerns were ignored. Preparing for the hearing, with a clear summary in the local language and honest answers about water use, land, traffic and emissions, protects the clearance later.

Validity and transfer

How long EC lasts and what happens on a change of owner

An EC is valid for a fixed period from the date of grant, within which the project must start. The EIA Notification, as amended, sets the validity by type of project: ten years for most projects, with longer periods for river valley and mining projects. If the project does not start within the validity, the clearance lapses and a fresh application is required. Extensions are possible only as the notification allows, so track the validity date from day one.

If the project is sold, merged or transferred, the EC can be transferred to the new owner through an application on PARIVESH, with the transferee accepting all the conditions. Until the transfer is approved, the original holder remains answerable for compliance. Buyers of projects should check the EC, the compliance reports, and any pending violation proceedings before completing the transaction.

Roles

Who does what in the EC process

BodyRole
Project proponentPrepares Form 1 and studies, engages an accredited consultant, attends hearings, complies with conditions
Accredited EIA consultantPrepares the EIA report and environmental management plan
State pollution control boardConducts the public hearing; consulted on air and water issues
Expert Appraisal Committee (EAC) or SEACAppraises the project and recommends grant or rejection
MoEFCC or SEIAADecides and issues the EC
MoEFCC regional office and the boardMonitor compliance with EC conditions
Do not let it slip

After you get EC

  • Display the EC and its conditions as required
  • File six-monthly compliance reports on PARIVESH
  • Do not change the project's scale, layout or product mix without checking whether an amendment is needed
  • Keep records of every condition, with photographs and test reports
  • Track the EC validity date until the project starts
  • Apply for transfer before or immediately after any change of ownership
FAQs

Frequently Asked Questions

Which projects need environmental clearance?

Projects and activities listed in the Schedule to the EIA Notification, 2006, above the specified thresholds.

Who grants EC?

MoEFCC for Category A projects and the SEIAA for Category B projects.

Is a public hearing always needed?

No. It is needed for Category A and B1 projects, with some exceptions in the notification.

Can I start construction while EC is pending?

No. Prior EC is mandatory before any construction or site work.

Is post-facto EC still possible?

Very limited. The Supreme Court quashed the 2021 route in July 2026, prospectively.

Do I need CTE if I have EC?

No separate CTE is needed since November 2024, though the CTE fee is payable and the board is consulted.

How long does EC take?

B2 projects can take a few months; B1 and A projects often take longer because of studies and hearings.

What is PARIVESH?

The online portal for environmental, forest, wildlife and CRZ clearances.

What happens if I breach EC conditions?

Directions, penalties and, in serious cases, suspension or revocation of EC.

Does an EC expire?

Yes, if the project does not start within the validity period set by the notification.

Planning a Project That May Need EC?

Send us the project details and location. We will confirm whether EC is needed, the category and the route.

This page gives general information about environmental law as it stood when it was last reviewed. It is not legal advice on your case and does not promise any result. Environmental rules, EPR targets, GRAP measures and board procedures change often, so check the current position for your unit or project before acting.