Live Chat +91 96259 41599
Environmental Law

Permission to Use Groundwater for Your Industry, Building or Project

Drawing groundwater through borewells? Who needs a groundwater NOC, CGWA or state authority, exemptions, abstraction charges, metering, renewal and penalties.

Advice and representation before the pollution boards, environment authorities and the National Green Tribunal, for industries, builders, hospitals, RWAs and residents, led by Advocate BK Singh.

Get A Free Consultation

Last reviewed: October 2026

Groundwater is under severe pressure in much of north India, and drawing it for industrial or commercial use needs permission. The Central Ground Water Authority regulates groundwater extraction under guidelines issued in September 2020, as amended, through an online No Objection Certificate system. In some states, a state authority under state law issues the permission instead: Uttar Pradesh has its own Ground Water (Management and Regulation) Act, 2019, and Haryana regulates through its Water Resources Authority. Drawing groundwater without a required NOC can lead to sealing of borewells, environmental compensation and penalties.

This page explains who needs a groundwater NOC, which authority to approach, the exemptions, the conditions such as meters and recharge, abstraction charges, renewal, and how to deal with enforcement.

Who needs itIndustries, infrastructure, mining, housing societies and commercial users drawing groundwater
Who grantsCGWA, or a state authority where state law applies
ConditionsMeters, piezometers, water audit, recharge
ExemptAgriculture and certain domestic and small users

рд╣рд┐рдВрджреА рдореЗрдВ рд╕рд╛рд░рд╛рдВрд╢

рдЙрджреНрдпреЛрдЧ, рдЗрдиреНрдлреНрд░рд╛рд╕реНрдЯреНрд░рдХреНрдЪрд░, рдЦрдирди, рд╣рд╛рдЙрд╕рд┐рдВрдЧ рд╕реЛрд╕рд╛рдЗрдЯреА рдФрд░ рдХрдорд░реНрд╢рд┐рдпрд▓ рдЙрдкрдпреЛрдЧ рдХреЗ рд▓рд┐рдП рднреВрдЬрд▓ (рдмреЛрд░рд╡реЗрд▓) рдирд┐рдХрд╛рд▓рдиреЗ рдкрд░ рдЕрдиреБрдорддрд┐ (NOC) рдЪрд╛рд╣рд┐рдП, рдЬреЛ рдХреЗрдВрджреНрд░реАрдп рднреВрдЬрд▓ рдкреНрд░рд╛рдзрд┐рдХрд░рдг (CGWA) рдпрд╛ рд░рд╛рдЬреНрдп рдХреЗ рдХрд╛рдиреВрди рдХреЗ рддрд╣рдд рд░рд╛рдЬреНрдп рдкреНрд░рд╛рдзрд┐рдХрд░рдг рджреЗрддрд╛ рд╣реИ, рдЬреИрд╕реЗ рдЙрддреНрддрд░ рдкреНрд░рджреЗрд╢ (рднреВрдЬрд▓ рдЕрдзрд┐рдирд┐рдпрдо 2019) рдФрд░ рд╣рд░рд┐рдпрд╛рдгрд╛ (рд╡реЙрдЯрд░ рд░рд┐рд╕реЛрд░реНрд╕реЗрдЬрд╝ рдЕрдереЙрд░рд┐рдЯреА)ред рдореАрдЯрд░, рдкреАрдЬрд╝реЛрдореАрдЯрд░, рд╡реЙрдЯрд░ рдСрдбрд┐рдЯ рдФрд░ рд░рд┐рдЪрд╛рд░реНрдЬ рдЬреИрд╕реА рд╢рд░реНрддреЗрдВ рд╣реЛрддреА рд╣реИрдВред рдмрд┐рдирд╛ NOC рдмреЛрд░рд╡реЗрд▓ рд╕реАрд▓ рд╣реЛ рд╕рдХрддрд╛ рд╣реИ рдФрд░ рдореБрдЖрд╡рдЬрд╝рд╛ рд▓рдЧ рд╕рдХрддрд╛ рд╣реИред

Check first

Is this your situation?

  • Your factory or project uses borewells for water
  • You are a housing society, mall, hotel or hospital drawing groundwater
  • You run a mine or construction project that needs dewatering
  • Your borewell has been sealed or you received a notice
  • Your groundwater NOC is due for renewal
  • You are in Uttar Pradesh or Haryana and unsure which authority applies
  • You are unsure whether your use is exempt
Key points

Groundwater NOC at a glance

Who regulates

The Central Ground Water Authority under its 2020 guidelines, or a state authority where state groundwater law applies.

Who needs an NOC

Industries, infrastructure, mining, bulk water supply, and commercial and group housing users, subject to the guidelines' exemptions.

Area assessment matters

Conditions and charges depend on whether the area is safe, semi-critical, critical or over-exploited.

Conditions

Digital flow meters, piezometers, water audits, rainwater harvesting and recharge, and reporting.

Abstraction charges

Charges based on the quantity drawn and the area's category.

Renewal

NOCs are time-limited and must be renewed before expiry.

Getting the forum right

CGWA or the state authority?

The first question is which authority regulates groundwater where your unit is. CGWA's guidelines apply in states that have not enacted their own groundwater law with a functioning authority. Where a state has its own law and authority, NOCs are issued under that law. In Uttar Pradesh, the Ground Water (Management and Regulation) Act, 2019 requires registration and NOCs for non-agricultural users through the state's system. In Haryana, the Water Resources (Conservation, Regulation and Management) Authority regulates groundwater use. Delhi, Rajasthan and other states have their own arrangements or rely on CGWA. Applying to the wrong authority wastes time and leaves the unit exposed. See CGWA.

Step by step

How to get a groundwater NOC

1

Confirm the authority

Identify whether CGWA or a state authority regulates groundwater at your site.

2

Check the area category

Find the groundwater assessment category of your block or area.

3

Calculate water demand

Prepare a water balance showing total demand, recycling and the groundwater quantity sought.

4

Prepare reports

Hydrogeological report where required, and recharge and conservation plans.

5

Apply online

Through the authority's portal with fees and documents.

6

Comply with conditions

Install meters and piezometers, implement recharge, conduct water audits and report as required.

When things go wrong

Sealing, compensation and penalties

Authorities and pollution boards have sealed borewells drawing groundwater without NOC, especially in over-exploited areas and in NCR, where the National Green Tribunal has repeatedly addressed illegal extraction. Environmental compensation has been imposed for past illegal extraction, calculated on the quantity drawn and the area category. If your borewell is sealed, gather evidence of any application, the quantity actually drawn, metering data and the purpose of use, and apply for NOC or de-sealing with an undertaking to comply. If an environmental compensation demand is raised, examine the calculation closely; errors in assumed quantity are common. See environmental compensation demand.

What to expect

Time and typical cost

Our fees are agreed in writing at the start, stage by stage. They are not linked to the outcome.

StageUsual timeWhat it involves
Authority and area check2 to 5 daysOur fee
Water balance and reports1 to 4 weeksHydrogeologist's fee
Application and processingVaries by authority; often 1 to 3 monthsApplication fee
Meters and recharge structuresWeeksEquipment and construction cost
Abstraction chargesAnnual or as notifiedBased on quantity and area
Paperwork

Documents usually needed

Site and use

  • Location with coordinates and land documents
  • Details of existing and proposed borewells

Water planning

  • Water balance and demand calculation
  • Recycling and reuse plan
  • Rainwater harvesting and recharge plan

Technical

  • Hydrogeological report where required
  • Meter and piezometer specifications
Legal basis

Laws that apply

Environment (Protection) Act, 1986, Section 3(3)

Basis for the Central Ground Water Authority.

CGWA Guidelines, 2020 (as amended)

NOC requirements, exemptions, conditions and charges.

Uttar Pradesh Ground Water (Management and Regulation) Act, 2019

State regime for groundwater in UP.

Haryana Water Resources (Conservation, Regulation and Management) Authority Act, 2020

State regime for water resources in Haryana.

Our approach

How we work

We are a litigation and advisory practice led by Advocate BK Singh, with offices in Dwarka (New Delhi) and Vaishali (Ghaziabad). This is what you can expect:

  • Right authority identified: CGWA or the state.
  • Water balance that holds up: demand, recycling and recharge.
  • Compliance set up: meters, piezometers and reporting.
  • Fast response to sealing: and compensation demands.
  • Written fee terms: agreed stage by stage, never linked to the outcome.
Avoid these

Mistakes we see with groundwater

  • Applying to CGWA when a state authority regulates the area
  • Drawing more than the NOC permits
  • Not installing meters or piezometers
  • Letting the NOC expire
  • Assuming a housing society is always exempt
Illustration

A Noida factory and the UP Act

Here's a made-up example. A Noida electronics factory had a borewell and an old CGWA application from years earlier. It assumed it was covered.

We checked and found that groundwater in Uttar Pradesh was now regulated under the state's 2019 Act. The factory registered and applied for an NOC under the state system, installed a digital flow meter and piezometer, and set up rainwater harvesting. The NOC was granted with conditions on recharge and reporting.

Illustration

A sealed borewell in Gurugram

Here's a second made-up example. A Gurugram housing society's borewell was sealed during an enforcement drive, and the society faced an environmental compensation notice.

We gathered records showing that the society had applied for permission and used the borewell only to supplement municipal supply during shortages, with metering. The society applied to the Haryana authority for permission with a recharge plan. The borewell was de-sealed on conditions, and the compensation was recalculated on the actual metered quantity.

Safe to over-exploited

What the area category means for you

Groundwater rules depend heavily on how stressed the area is. Assessment units, usually blocks, mandals or talukas, are categorised on the basis of the stage of groundwater extraction: safe where extraction is up to 70 per cent of annual extractable resource, semi-critical from 70 to 90 per cent, critical from 90 to 100 per cent, and over-exploited above 100 per cent. Large parts of Haryana, Punjab, Rajasthan, western Uttar Pradesh and Delhi fall in the critical or over-exploited categories.

The category affects whether new extraction is allowed, the abstraction charges, and the conditions on recharge and reuse. In over-exploited areas, new industries and projects face strict limits, and some kinds of use, such as packaged drinking water units, face additional scrutiny. Check the current assessment for your block before planning any project that relies on groundwater.

A frequent enforcement issue

Dewatering during construction

Basements and foundations often require pumping out groundwater, and large construction sites in NCR have been penalised for dewatering without permission or for discharging the water into drains. Dewatering usually needs a separate permission under the CGWA guidelines or the state law, with conditions on measuring the quantity, using the water for construction, supplying it to the local body, or recharging it. The NGT has repeatedly addressed illegal dewatering in Delhi NCR. If your project has a deep basement, build dewatering into your approvals plan from the start.

Keep evidence

Typical NOC conditions and how to prove compliance

ConditionEvidence to keep
Digital flow meter on each borewellMeter photographs, calibration and monthly readings
Piezometer for water level monitoringInstallation report and water level records
Rainwater harvesting and rechargeDesign, photographs and maintenance records
Water auditAudit reports at the required frequency
Reuse of treated waterSTP or ETP records showing quantities reused
Reporting to the authorityCopies of returns filed on the portal
Commercial and group users

Housing societies, hotels and hospitals

Group housing societies, malls, hotels, hospitals and institutions often assume groundwater rules are only for factories. They are not. Under the CGWA guidelines and state laws, many such users need permission, though individual households and some small users are exempt. Housing societies that depend on borewells because municipal supply is inadequate should apply for permission, meter their extraction and recharge, rather than wait for an enforcement drive. Where a society or building has an STP, using treated water for flushing and gardens reduces the groundwater demand and strengthens the application.

FAQs

Frequently Asked Questions

Who needs a groundwater NOC?

Industries, infrastructure, mining, bulk water suppliers and many commercial and housing users, subject to exemptions.

Who issues it?

CGWA, or a state authority where state law applies, as in Uttar Pradesh and Haryana.

Is agriculture exempt?

Agricultural use is generally exempt under the CGWA guidelines.

What are abstraction charges?

Charges based on the quantity of groundwater drawn and the area's category.

What conditions come with the NOC?

Meters, piezometers, water audits, recharge and reporting.

How long is the NOC valid?

For a limited period set by the authority; renew before expiry.

What if my borewell is sealed?

Apply for NOC or de-sealing with evidence and an undertaking to comply.

Can environmental compensation be demanded for past extraction?

Yes, calculated on the quantity drawn; check the calculation carefully.

Does a building with EC need a groundwater NOC?

If it draws groundwater, usually yes.

Can I drill a new borewell in an over-exploited area?

New extraction is heavily restricted in such areas; take advice first.

Using Groundwater?

Send us your site location and water use. We will identify the right authority and handle the NOC.

This page gives general information about environmental law as it stood when it was last reviewed. It is not legal advice on your case and does not promise any result. Environmental rules, EPR targets, GRAP measures and board procedures change often, so check the current position for your unit or project before acting.

Need help with Permission to Use Groundwater for Your Industry, Building or Project?

Send us the notice, the order or a few photos. We'll tell you where you stand, which authority or NGT bench deals with it and when the next step is due, in plain words.

 +91-9315261599 Schedule Your Consultation