Which Environmental Permissions Does My Business Need?

Which environmental permissions apply to your factory, project or brand: CTE, CTO, EC, groundwater NOC, EPR, and what to do if one is refused or delayed.

Written by the environmental law practice of Advocate BK Singh, which acts before the pollution boards, environment authorities and the National Green Tribunal.

Get A Free Consultation

Last reviewed: October 2026

Most businesses that make, build, pack or import goods in India need at least one environmental permission, and many need four or five. A factory needs consent to establish (CTE) before construction and consent to operate (CTO) before production. Large projects and buildings of 20,000 sq m and above need environmental clearance (EC). Drawing groundwater usually needs a NOC. Brand owners and importers of plastic packaging, electronics and batteries need EPR registration with the CPCB. If a permission is refused, there is an appeal. If it is delayed, there is a way to push it.

Short answer: Most factories need consent to establish before building and consent to operate before production from the State Pollution Control Board. Listed projects and buildings of 20,000 sq m and above also need environmental clearance, most groundwater users need a NOC, and producers, importers and brand owners of plastic packaging, electronics and batteries need EPR registration.

This page is the overview. It tells you which permissions apply to your kind of business, who grants each one, and what to do when the file gets stuck or comes back refused. Where a topic needs more depth, we point you to the detailed guide, such as the difference between CTE and CTO or EC for building projects.

We start with the question owners ask us most often: what to do when the pollution board sits on a consent file or refuses it.

Consent lawWater Act s.25, Air Act s.21
Appeal on consentAppellate authority, 30 days
EC for buildings20,000 sq m and above
White categoryExempt from consent
Next appealNGT, s.16, 30 days
EPR portalCPCB centralised portal

हिंदी में सारांश

किसी भी फैक्ट्री को निर्माण से पहले प्रदूषण नियंत्रण बोर्ड से कंसेंट टू एस्टैब्लिश (CTE) और उत्पादन से पहले कंसेंट टू ऑपरेट (CTO) लेना होता है। व्हाइट श्रेणी की इकाइयों को छूट है। बड़े प्रोजेक्ट और 20,000 वर्ग मीटर या उससे बड़ी इमारतों को पर्यावरण मंजूरी (EC) चाहिए। भूजल निकालने के लिए अधिकतर मामलों में NOC जरूरी है। प्लास्टिक पैकेजिंग, इलेक्ट्रॉनिक्स और बैटरी के ब्रांड मालिकों और आयातकों को CPCB पोर्टल पर EPR पंजीकरण कराना होता है। अगर कंसेंट अस्वीकार हो जाए तो 30 दिन के अंदर राज्य की अपीलीय प्राधिकरण में अपील करें, और उसके बाद NGT में। बिना अनुमति के यूनिट न चलाएं, इससे जुर्माना, बंदी और पर्यावरण क्षतिपूर्ति हो सकती है।

In short

The essentials

CTE, then CTO

Get consent to establish before you build and consent to operate before you start production.

Check your colour

Your CPCB category (red, orange, green or white) decides how strict the consent process is, and white units are exempt.

EC for big projects

Listed projects and buildings of 20,000 sq m and above need prior environmental clearance under the EIA Notification 2006.

Groundwater NOC

Industrial, infrastructure, mining and bulk users of groundwater usually need a NOC from the CGWA or the state authority.

EPR for brands

Producers, importers and brand owners of plastic packaging, electronics and batteries must register on the CPCB portal.

30 days to appeal

A refused consent can be appealed to the state appellate authority within 30 days, and then to the NGT.

Refused or stuck

My consent to establish or operate was refused or is delayed. What can I do?

Start by finding out exactly where the file is. Log in to the board's online consent system and read the status and every remark. In most delayed files, the board raised a query weeks ago, nobody noticed, and the file sits as 'pending with applicant'. If there is a query, answer it fully, point by point, with documents, and keep proof of the upload date.

If there is no query and the file has simply crossed the board's own timeline, write to the regional officer and then to the Member Secretary, quoting the application number, the date of filing, the fee paid and the inspection date if one took place. Ask for a decision or a written list of deficiencies. A dated reminder on the file does more than repeated visits, because it builds a record. An RTI application for the file notings and inspection report also helps; the reply is due within 30 days.

Do not assume that silence means yes. Deemed consent exists only where the statute or a state's rules expressly provide for it, in the stated situation, and boards read such provisions narrowly. Check the current rule for your state and category before relying on it. Owners who 'went ahead on deemed consent' often end up defending a closure notice.

If the consent is refused, or granted with conditions you cannot live with, the first appeal lies to the state appellate authority under section 28 of the Water Act and section 31 of the Air Act, within 30 days. Read the refusal order closely first. If it cites a prohibited zone, the appeal is a serious fight. If it cites a missing document or a weak treatment design, a fresh application with the gap fixed is usually faster. We cover the process on our appellate authority page.

If the appellate authority also rules against you, the next appeal goes to the National Green Tribunal under section 16 of the NGT Act, within 30 days of the order being communicated (the NGT can allow up to 60 more days for sufficient cause). Through all of this, one rule does not change: do not start construction without CTE and do not run the unit without CTO. A pending appeal is not permission.

At a glance

Environmental permissions: who needs them, who grants them, which law

This is the master list. Most businesses need only some of these, and the next sections explain how to tell which.

PermissionWho needs itWho grants itLaw
Consent to establish (CTE)Red, orange and green category units, before constructionState Pollution Control Board or Pollution Control Committee (DPCC in Delhi)Water Act s.25, Air Act s.21
Consent to operate (CTO)The same units, before production and on renewalState Board or CommitteeWater Act s.25, Air Act s.21
Environmental clearance (EC)Projects listed in the EIA Notification, and buildings of 20,000 sq m built-up area and aboveSEIAA (category B) or the Union environment ministry (category A)EIA Notification 2006 under the EP Act
Groundwater NOCIndustrial, infrastructure, mining and bulk users drawing groundwaterCGWA, or the state groundwater authority where one existsCGWA guidelines 2020 (as amended), state groundwater laws
Hazardous waste authorisationUnits generating or handling hazardous waste such as used oil or ETP sludgeState Board or CommitteeHazardous Waste Rules 2016
Bio-medical waste authorisationHospitals, clinics, labs, blood banks and treatment facilitiesState Board or CommitteeBio-Medical Waste Rules 2016
Plastic EPR registrationProducers, importers and brand owners (PIBOs) of plastic packagingCPCB (or the State Board for some smaller entities), on the centralised portalPlastic Waste Management Rules 2016, EPR guidelines 2022
E-waste EPR registrationProducers, importers, refurbishers and recyclers of listed electronicsCPCB portalE-Waste (Management) Rules 2022
Battery EPR registrationProducers and importers of batteries, including batteries fitted in productsCPCB portalBattery Waste Management Rules 2022
Tree felling permissionAnyone cutting or transplanting trees, even on private landTree officer, forest department or local body under the state's tree lawState tree protection laws; forest law for forest land

Fire NOC, building plan sanction and factory licence sit outside environmental law, but boards often ask for them, so keep them ready.

Categories

Is my unit in the red, orange, green or white category?

Your category comes from the CPCB's list of industrial sectors, which each state board adopts with its own tweaks. The colour reflects how polluting your process is, not how big your unit is. A small electroplating shop can be red while a large garment stitching unit may be green or white. Look up your exact process, not your trade name, in the current list.

Red category units (many chemical, pharmaceutical, dyeing and tannery processes, for example) face the strictest scrutiny, shorter consent periods and more inspections, and are generally kept out of residential and sensitive areas. Orange sits in the middle; green gets lighter treatment and longer validity. White category units are exempt from consent altogether, though they may still need to inform the board, and they still have to follow the law on noise, waste and water use.

Two mistakes come up again and again. The first is describing the process loosely to land in a lighter category. Inspectors look at the machinery and raw material, not the label. The second is adding a process (say, a small painting or plating line) without realising it pushes the whole unit into a higher category. That needs fresh consent, not just a renewal.

The consent rules have also been changing. Amendments and notifications in 2024 and 2025 altered some requirements, including exemptions. Do not rely on what a neighbouring unit did three years ago: check the current notification and your board's latest office orders before you file. Our consent to establish page explains the filing. Advocate B.K. Singh's usual advice to a new unit is to settle its category in writing with the board before buying machinery, because a wrong assumption about the category is the most expensive mistake to undo later.

Environmental clearance

Do I need EC as well as consent?

Yes, if your project is listed, and EC does not replace consent. Environmental clearance under the EIA Notification 2006 is a project-level approval decided before work starts; consent is the pollution board's permission to build and run a source of pollution. The board will usually want to see the EC before it grants CTE.

EC applies to the projects listed in the Schedule to the EIA Notification: mining, power, large industrial and infrastructure projects among them, with thresholds that decide whether the project is category A (decided by the Union environment ministry) or category B (decided by the State Environment Impact Assessment Authority, the SEIAA). For builders, the line that matters is 20,000 sq m of built-up area. At and above it, the project needs prior EC, generally from the SEIAA. Townships and area development projects of 1,50,000 sq m and above fall in a higher category.

The word 'prior' matters. The Supreme Court in Alembic Pharmaceuticals v Rohit Prajapati (2020) came down hard on ex post facto EC, and the law on regularising projects that started without EC has shifted in later decisions. If your project has already started without EC, get advice on the current position before you file anything, because the wrong application can amount to an admission. Our environmental clearance page covers the process.

Groundwater

Do I need a groundwater NOC? Who is exempt?

If your business draws groundwater through a borewell or tubewell for industrial, infrastructure, mining or bulk supply use, you almost certainly need a NOC. The CGWA guidelines of 2020 (as amended) cover most such users across the country. Packaged water units, construction sites, hotels, malls, group housing and many factories fall in this net.

Individual domestic users, agricultural users and certain small users are exempt under the CGWA guidelines. The exact limits and conditions for 'small' depend on the current version of the guidelines and on where you are, so read our groundwater NOC exemption guide before you assume you are outside it.

Several states run their own groundwater authority with their own Act or rules, and in those states the NOC usually comes from the state body, not the CGWA. Where the area is classified as over-exploited or critical, the conditions get much tighter: water audits, metering with telemetry, recharge structures and sometimes outright refusal for new industrial use. A plot in an over-exploited block may be cheap for a reason. Our groundwater NOC page explains the application and renewal.

EPR

Do I need EPR registration for plastic, e-waste or batteries? What are the targets?

You need EPR registration if you put certain products or packaging on the Indian market, whether or not you manufacture anything yourself. EPR makes the producer, importer or brand owner answer for the waste their product becomes. You register on the CPCB's centralised portal and file returns on it every year.

Under the Plastic Waste Management Rules and the EPR guidelines of 2022, the obligation falls on producers, importers and brand owners (PIBOs). If you sell anything in plastic packaging under your own brand, you are a brand owner, even if a contract manufacturer packs it. Importers of goods in plastic packaging are covered too. Our guide on who needs plastic EPR goes through the edge cases.

The E-Waste (Management) Rules 2022 apply to manufacturers, producers, importers, refurbishers and recyclers of the listed electrical and electronic equipment. Importers, who see themselves as traders, are most often caught out. See our e-waste EPR guide for importers. The Battery Waste Management Rules 2022 cover producers and importers of batteries, including batteries that come fitted in vehicles, inverters and devices, which brings EV makers and equipment importers in. Our battery EPR page covers that.

Targets under all three rules are set as percentages of what you place on the market, and they rise year by year. We do not quote the numbers here because they differ by product and year and are revised. The practical point is that you meet them by buying EPR certificates from registered recyclers or processors, or by running your own collection system, and that unmet targets attract environmental compensation. Keep your sales and import data clean, because returns are checked.

Other permissions

Hazardous waste, bio-medical waste and tree felling: the ones people forget

Hazardous waste authorisation is needed by more units than owners realise. Used oil from a DG set or machinery, spent solvents, paint sludge, ETP sludge and empty chemical drums are hazardous waste under the Hazardous Waste Rules 2016. If you generate, store or send them out, you need authorisation from the state board, a proper storage area, manifests for every consignment and annual returns. Our hazardous waste authorisation page has details.

Bio-medical waste authorisation applies to every hospital, nursing home, clinic, dental practice, pathology lab and blood bank that generates such waste, and to common treatment facilities. Small clinics often assume it is only for hospitals. It is not.

Tree felling permission is the one that stops building projects in their tracks. Cutting or transplanting trees on a site, even private land, usually needs permission from the tree officer or forest department under the state's tree protection law, often with compensatory planting or a deposit. Forest land needs separate forest clearance. Get the tree survey done before you finalise the layout.

By business type

Which permissions usually apply to you

A first cut by type of business. Your actual list depends on process, size and location.

Your businessPermissions usually neededOften missed
Factory or workshop (red, orange or green category)CTE, CTO, hazardous waste authorisationGroundwater NOC for a borewell; fresh consent after expansion
Builder of a housing or commercial projectEC at 20,000 sq m and above, CTE and CTO (for the building and its STP), groundwater NOCTree felling permission; dewatering NOC during construction
Brand owner selling packaged goodsPlastic EPR registration and annual returnsEPR when the goods are made by a contract manufacturer
Importer of electronics or batteriesE-waste EPR, battery EPR, plastic EPR for packagingBattery EPR for batteries fitted inside imported products
Hospital, clinic or labBio-medical waste authorisation, CTE and CTO for larger facilitiesHazardous waste authorisation for DG set used oil
Hotel, mall or warehouseCTE and CTO where applicable, groundwater NOCDG set compliance and STP consent conditions
Before you start

Permissions checklist before you start a unit

Work through this before you sign the lease. Dropping a site now is far cheaper than fighting a refusal later.

1

Pin down your exact process

List raw materials, products, machinery, fuel, water use and waste. Your category follows from this, not your business name.

2

Find your category

Look up the process in your state board's current red, orange, green and white list, and check any recent exemption notifications.

3

Check the site

Confirm the land use permits industry, the site is outside prohibited or eco-sensitive zones, and the groundwater block is not over-exploited.

4

Check if EC applies

See if your project is listed in the EIA Notification 2006, or if your building crosses 20,000 sq m of built-up area. If yes, EC comes first.

5

Apply for groundwater NOC and tree permission

If you will draw groundwater or cut trees, apply early; these often take longer than consent.

6

Apply for CTE

File on the board's portal with site plan, process flow and pollution control design. Do not build until it is granted.

7

Build to the CTE conditions

Install the ETP, STP, stack or scrubber exactly as approved, and keep photos and invoices.

8

Apply for CTO and waste authorisations

Apply for CTO, with hazardous or bio-medical waste authorisation where relevant, before trial production. Start operation only after the CTO is in hand.

9

Register for EPR if you sell or import

Producers, importers and brand owners of plastic packaging, electronics or batteries register on the CPCB portal before selling.

10

Diary every renewal date

Note expiry dates of CTO, NOC and authorisations, and file renewals well ahead. Our guide on how long CTO takes helps with planning.

Paperwork

Documents to keep ready

Boards ask for much the same set across states. For a fuller list see documents for consent to operate.

For CTE and CTO

  • Ownership or lease deed of the site
  • Site plan and layout with drainage and stack locations
  • Land use or zoning certificate
  • Process flow chart with raw materials and products
  • Pollution control design (ETP, STP, APCD) with capacity
  • Water balance and source of water
  • Capital investment proof (CA certificate)
  • Copy of CTE and compliance report (for CTO)

For EC and groundwater NOC

  • Form for EC with project details and built-up area statement
  • Environmental studies or EIA report where required
  • Hydrogeological report for groundwater
  • Water requirement calculation
  • Recharge plan and meter details
  • Tree survey for the site

For EPR and waste

  • GST, IEC and company documents
  • Product-wise sales or import data
  • Category-wise packaging quantities
  • Agreements with recyclers or processors
  • Hazardous waste storage details and TSDF membership
  • Manifests and annual returns
Consequences

What happens if I operate without permission?

Three things can happen, often together: a monetary penalty, closure, and environmental compensation. After the Jan Vishwas (Amendment of Provisions) Act 2023 and the Water (Prevention and Control of Pollution) Amendment Act 2024, many violations under the Water Act, Air Act and EP Act that used to be criminal offences now carry monetary penalties decided by an adjudicating officer. Our guide on penalty for running without CTO explains the process.

Closure is the bigger worry for most owners. Under section 33A of the Water Act, section 31A of the Air Act and section 5 of the EP Act, the board can order closure, prohibit operation or direct the electricity and water supply to be cut. A show-cause notice usually comes first, and a documented reply at that stage matters, as our guide on closure notice options explains. Boards do revoke closure once compliance is shown, often with conditions or a bank guarantee, but lost weeks of production cost more than the consent.

Environmental compensation is calculated using the CPCB's formula, which multiplies factors such as a pollution index for your industry category, the number of days of violation, the size of the unit and its location. Every day of running without consent adds to the figure. The NGT applies the polluter pays principle, and it does not treat 'the application was pending' as an excuse for running without consent. If you have a notice, get it read before you reply, and apply for consent at once.

Illustration

A packaged water unit that nearly started too early

Here's a made-up example. Ravi takes a shed in an industrial area near Ghaziabad to bottle packaged drinking water under his own brand. His raw material is groundwater from a borewell, he plans a DG set for backup, and his bottles and caps are plastic.

His consultant files only for consent. Two months on, the CTO is still pending, the machinery has arrived, and Ravi is tempted to begin trial runs. On the portal he finds a five-week-old query: the board wants proof of a groundwater NOC and details of how used oil from the DG set will be handled.

He holds off. He applies for the groundwater NOC, files for hazardous waste authorisation with a tie-up with an authorised recycler, and replies to the query with both. He also registers on the CPCB portal as a brand owner under the plastic EPR rules, since his bottles carry his brand. The CTO comes through after the NOC.

Had he started on the strength of a 'pending' application, he would have been running without consent, without a groundwater NOC and without EPR registration, three separate violations on day one. The delay cost him a few weeks. The shortcut could have cost him the unit.

What goes wrong

Mistakes we see most often

  • Starting on a pending file. An application is not a consent, and neither is a fee receipt or an inspection.
  • Missing portal queries. Most 'delayed' files are waiting for the applicant's reply, not the board's decision.
  • Expanding without fresh consent. More production, a new product line or an extra boiler needs fresh CTE, not just a CTO renewal.
  • Appealing a fixable refusal. If the refusal is about a missing document, reapplying is usually faster than an appeal.
  • Treating EPR as optional for traders. Importers and brand owners are covered even if they never touch a machine.
FAQs

Frequently Asked Questions

Can I start construction after applying for CTE?

No. You need the CTE order in hand before you start construction or install machinery. Starting on an application is treated as establishing without consent.

How long do I have to appeal a refused consent?

30 days from the refusal, to the state appellate authority under Water Act s.28 and Air Act s.31. Against the appellate order, you can go to the NGT within 30 days of communication.

Is there deemed consent if the board does not decide?

Only where the law or your state's rules expressly provide it, and only in the stated situation. Check the current rule and get it confirmed in writing before relying on it.

Do white category units need any permission?

White category units are exempt from consent. They still have to follow rules on noise, waste and water, and may need other permissions such as a groundwater NOC.

My building is 18,000 sq m. Do I need EC?

Not under the 20,000 sq m building threshold, but measure built-up area the way the EIA Notification counts it, and remember a later expansion can cross the line.

I use a borewell only for my staff toilets. Do I need a groundwater NOC?

Possibly not, as some small users are exempt, but the limits depend on the current CGWA guidelines and your state's rules. Check before you assume.

I only import goods. Am I a producer under EPR?

Yes, for EPR purposes importers of plastic-packaged goods, listed electronics and batteries carry producer obligations and must register on the CPCB portal.

What are the EPR targets for this year?

Targets are percentages of what you place on the market and rise each year. They vary by product and are revised, so check the current figures on the CPCB portal.

What is the penalty for running a factory without CTO?

After the 2023 and 2024 amendments, an adjudicating officer can impose monetary penalties. The board can also order closure and the CPCB formula can be used for environmental compensation.

My CTO renewal is pending and the old one expired. Can I keep running?

Not safely. Unless a rule expressly protects you during renewal, running after expiry is running without consent. File renewals well before the expiry date.

BK

About the author

Advocate B.K. Singh, Founder & Principal Advocate, MCA, LL.B., LL.M.

Advocate B.K. Singh has practised for more than twenty years before the Supreme Court, the High Courts and the National Green Tribunal, and leads the environmental practice from offices in Dwarka (New Delhi) and Vaishali (Ghaziabad) with Advocate Sadhna Singh. Read his profile.

Stuck on a consent, EC, NOC or EPR file?

Send us the refusal order, the portal status or a short description of your unit on WhatsApp or by phone. We will tell you which permissions you need and the next step.

This page gives general information about environmental law as it stood when it was last reviewed. It is not legal advice on your case and does not promise any result. Laws, rules, fees and time limits change, so check the current position for your matter before acting.