If your factory's effluent treatment plant is not working and effluent is leaving the premises, you are in breach of your consent to operate, and the State Pollution Control Board can direct closure and stop your electricity and water under section 33A of the Water Act. It can also levy environmental compensation for every day of violation, and residents can take the unit to the NGT. The legal risk is not the breakdown itself. It is a breakdown that is hidden, left unrepaired, or managed by letting untreated effluent out. How you act in the first few days decides how serious it becomes.
This guide is written for factory owners, directors and plant managers. It covers what the board treats as a non-working ETP, why ETPs fail, the legal consequences, what to do the day the plant breaks down, how to handle the inspection and the notice that follows, and how to get a closure revoked.
If you are a resident dealing with a unit whose ETP is not running, see our guide on complaining about untreated industrial effluent and the wider page on industrial effluent and water pollution remedies.
हिंदी में सारांश
अगर फैक्ट्री का ETP (एफ्लुएंट ट्रीटमेंट प्लांट) काम नहीं कर रहा और गंदा पानी बाहर जा रहा है, तो यह संचालन की सहमति (CTO) की शर्तों का उल्लंघन है। राज्य प्रदूषण नियंत्रण बोर्ड जल अधिनियम की धारा 33A के तहत फैक्ट्री बंद करने और बिजली-पानी काटने का आदेश दे सकता है, और हर दिन के उल्लंघन के लिए पर्यावरण क्षतिपूर्ति लगा सकता है। ETP खराब होते ही उत्पादन रोकें या घटाएं, गंदे पानी को स्टोर करें, बोर्ड को लिखित सूचना दें, जल्दी मरम्मत कराएं और पूरा रिकॉर्ड रखें। खराबी छिपाना या बिना साफ पानी छोड़ना सबसे बड़ा जोखिम है। बोर्ड के निर्देश के खिलाफ 30 दिन में NGT में अपील हो सकती है।
The essentials
Breakdown is a breach
Your consent to operate assumes a working ETP; effluent leaving without treatment breaches it.
Closure is on the table
The board can direct closure and cut power and water under Water Act s.33A after a show-cause notice.
Days add up
Environmental compensation is worked out per day of violation, so the length of the breach matters.
Records protect you
Logbooks, meter readings and a written breakdown report are your best defence on the number of days.
Tell the board first
A unit that reports a breakdown and fixes it is treated very differently from one caught hiding it.
30 days to appeal
A closure direction can be appealed to the NGT under s.33B within 30 days of communication.
Our ETP is not working. What are the legal risks?
Five, in rough order of how fast they arrive. The board can issue a show-cause notice and then direct closure of the unit and disconnection of electricity and water under section 33A of the Water Act. It can levy environmental compensation using the CPCB method, which multiplies factors including the number of days of violation. It can refuse or delay renewal of your consent to operate, or add tougher conditions such as a bank guarantee. The unit and the people in charge can face penalty proceedings under the Water Act, which after the 2024 amendment are largely decided by an adjudicating officer. And residents or farmers affected by the effluent can file an application in the NGT, which may order restoration and compensation on top of what the board has done.
None of this follows automatically from a pump failing on a Tuesday. Boards understand that machinery breaks. What they act hard against is a unit that keeps producing while the ETP is down and lets the effluent go, a unit whose ETP was never adequate for its production, and a unit that runs the plant only on inspection days. The question an inspector is really asking is whether this is an accident or a habit.
When Advocate B.K. Singh is asked to advise a unit after an ETP failure, the first thing he wants to see is the logbook and the electricity readings for the ETP over the previous three months, because those two records usually show whether the board will see a breakdown or a pattern.
What the board treats as an ETP 'not working'
More situations than owners expect. The obvious one is a plant that is switched off or broken, with effluent going out raw. But inspection reports also record an ETP as non-functional when the aeration tank has no live biomass, when the clarifier is overflowing sludge, when chemical dosing tanks are empty, when the tertiary filters or RO are bypassed, when sludge drying beds are full and sludge is being dumped elsewhere, or when the plant is running but the outlet fails the consent standards.
Inadequacy counts too. If your consent was granted for a certain production and effluent volume and you have since added machines or shifts, the ETP may be running perfectly and still be too small. The board compares your water consumption, production and treated effluent volume; if more water goes in than can be accounted for, it will ask where the rest went. Meters that do not work, or a separate electricity meter for the ETP that shows almost no consumption, lead to the same suspicion.
Finally, there is the bypass. Any pipe, hose or channel that lets effluent reach a drain, sewer, pit or open land without passing through the treatment units is treated as deliberate. Even an emergency overflow line that is used regularly will be seen this way.
Common ETP failures and what follows
| Failure | What the inspector records | Likely consequence |
|---|---|---|
| Plant switched off, raw effluent out | ETP non-operational, discharge observed | Show-cause, closure, disconnection, compensation |
| Biological stage dead after shock load | No biomass, outlet exceeds standards | Notice, time to restore, compensation for days of breach |
| Production increased beyond consent | ETP inadequate for present load | Notice, direction to upgrade, consent expansion required |
| Bypass pipe or emergency line in use | Bypass found, deliberate discharge | Closure and disconnection, heavier compensation |
| Sludge dumped on open land | Hazardous waste mismanagement | Action under the Hazardous Waste Rules and Water Act |
| Flow or electricity meters not working | Records unreliable | Adverse inference on days of non-operation |
| Outlet within norms but consent says ZLD | Discharge in breach of ZLD condition | Notice, closure, compensation |
What to do the day the ETP breaks down
These steps are about limiting both the pollution and the legal damage. They work best when done in this order and written down as you go.
Stop the effluent leaving
Cut or stop the production lines that generate effluent, or divert effluent to equalisation or holding tanks. Do not open a bypass to keep the factory running.
Record the failure
Note the time, the unit that failed (blower, pump, dosing, membrane), the cause if known, and what was done. Take photos of the failed equipment and the holding tank levels.
Inform the board in writing
Email or write to the board's regional office the same day or the next, describing the breakdown, the steps taken to stop discharge and the expected repair time. Many consent orders require this; read yours.
Repair or arrange alternatives
Call the vendor or technician, order parts and keep the bills. If storage will run out, send effluent only through authorised arrangements, for example by tanker to a CETP that accepts it, with records of each trip.
Restart and test
After repair, restart the plant gradually, especially the biological stage, and test the outlet at a recognised laboratory before resuming full production.
Report back to the board
Write again confirming the repair, the date full treatment resumed, and the test result. Attach the bills and photos.
Fix the cause
If the failure came from overload, poor design or no trained operator, commission a review and act on it before the next inspection finds the same weakness.
The Environment (Protection) Act (section 9) also places a duty on whoever is responsible for a discharge in excess of standards, caused by an accident or unforeseen event, to prevent or reduce it and to inform the authorities. A written breakdown report is how you show you met that duty.
The provisions that apply
Your consent to operate sets the volume and quality of effluent, the treatment system, where treated effluent may go (if anywhere) and record-keeping. A non-working ETP breaches these conditions, and breach of consent conditions is a ground for revocation or refusal of renewal.
The board can direct closure, prohibition or regulation of the unit and stoppage of electricity, water or other services. A show-cause notice and hearing normally come first. An appeal against the direction lies to the NGT under s.33B within 30 days, extendable by 60 days for sufficient cause.
ETP sludge from many industrial processes is hazardous waste. It needs authorisation from the board, safe storage within limits, transport by an authorised transporter under a manifest, and disposal at an authorised facility such as a TSDF. Dumping it on land is a separate breach.
Boards and the CPCB use a formula that multiplies a pollution index for the industry category, the number of days of violation, a scale factor for the unit's size and a location factor. Your records directly affect the number of days counted.
Residents can bring an application within 6 months (or 5 years for compensation). The NGT applies the polluter pays principle and can order restoration of the environment and compensation to victims.
Why ETPs fail, and why it matters legally
Most ETP failures we see are not mechanical accidents. They are the result of decisions made months earlier. The commonest is growth: the unit adds machines, a second shift or a new product, but the ETP stays the size it was when consent was granted. The plant then runs overloaded, the biological stage cannot keep up, and the outlet drifts out of norms. Legally this is doubly bad, because the expansion itself may have needed consent and the board will see the ETP failure as a symptom of operating beyond permission.
The second cause is design. Small units often buy a packaged ETP from a vendor without a treatability study of their actual effluent. When the effluent turns out to be more saline, more acidic or more toxic than the design assumed, no amount of operation fixes it. The third is operation: no trained operator, no daily testing, chemicals not dosed to save money, blowers switched off at night to cut the electricity bill. Inspectors look for exactly these signs.
The fourth is sludge. A plant that cannot get rid of its sludge stops working, because tanks fill and the clarifier carries sludge over to the outlet. Units that have not tied up with an authorised TSDF or arranged for authorised transport often end up dumping sludge, which creates a second, more serious violation. Our guide on hazardous waste manifests and transport covers that side.
Records that protect you on inspection day
Keep daily
- ETP logbook: flow in and out, hours run, operator signature
- Flow meter readings at inlet and outlet
- Separate electricity meter reading for the ETP
- Chemical dosing and consumption
- Basic tests: pH, and others your consent requires
Keep on file
- Current CTE and CTO with all conditions
- ETP design basis and commissioning report
- Monthly outlet reports from a recognised laboratory
- Hazardous waste authorisation, manifests and TSDF receipts
- Breakdown reports and letters to the board
- Repair bills and maintenance contracts
- CETP membership and tanker records, if applicable
How to reply to a show-cause notice about the ETP
Reply within the time given, even if only to ask for documents or a short extension, and keep proof of delivery. A reply that arrives after the board has already passed a closure direction is far less useful. Ask for a copy of the inspection report and the sample analysis if they were not enclosed; you cannot answer properly without them.
The reply should do three things. State the facts honestly: what failed, when, and what was done. Answer the specific findings: if the report says the meter was not working, show the replacement bill; if it says the outlet exceeded standards, explain when that sample was taken in relation to the breakdown and attach later test results. And show the remedy: repairs completed, an upgrade ordered, an operator hired, a sludge contract signed, with documents. Offer a time-bound plan for anything not yet done.
Where the board's findings are wrong, say so with particulars. A sample taken from the equalisation tank rather than the final outlet, an inspection during a reported and documented breakdown, or a misreading of the consent condition are all legitimate grounds. What does not work is a blanket denial of something the inspector photographed. Our page on pollution control board notices explains how we prepare these replies.
The board has ordered closure or cut our power. How do we get it revoked?
Usually by proving compliance and applying for revocation, rather than by fighting the order head on. Boards revoke closure directions when the unit shows the ETP is repaired or upgraded and working, often after a fresh inspection and sample, and often on conditions such as a bank guarantee that is forfeited if the breach recurs. Some boards also require payment of the environmental compensation assessed, or an undertaking about it, before revocation.
If the direction itself is unjustified, for example it was passed without a proper hearing, rests on a sample that was not taken from the outlet, or is out of proportion to a short documented breakdown, an appeal to the NGT under section 33B is available within 30 days of communication. The two routes can run together: apply for revocation while preserving the appeal. Missing the 30 days leaves only the 60-day extension, which needs sufficient cause. Our pages on closure notices and electricity and water disconnection by the board cover this in more detail.
How environmental compensation for an ETP failure is worked out
The board does not pick a number. It applies the CPCB methodology, which multiplies a pollution index for your industry category, the number of days of violation, a rupee factor, a scale factor for the size of the unit and a location factor. You cannot change your category or size, but you can affect the number of days, and that is where records matter.
If the board has no clear evidence of when the ETP stopped working, it may count from the last date it was known to be functioning, or from an earlier inspection, which can multiply the amount. A logbook showing normal operation up to a specific breakdown date, a letter to the board reporting the breakdown, and a test report after restart give you a firm start and end date. Units without records often end up arguing about months instead of days.
Environmental compensation can be challenged before the authority that imposed it and, depending on the order, in appeal. Our guide on what environmental compensation means explains the basis, and the page on environmental compensation demands covers challenges.
A formulation unit that doubled its output
Here's a made-up example. A pharmaceutical formulation unit got consent with an ETP sized for one shift. Over two years it added a second shift and two new product lines. The ETP's biological stage, already stretched, collapsed after a batch of solvent-heavy washwater. The plant manager kept production going and let the clarifier overflow into the stormwater drain 'for a few days'.
A resident complained, and the board inspected. The report recorded no live biomass, outlet samples far above standards, a dry sludge bed and an ETP electricity meter showing low consumption for months. The board issued a show-cause notice, then directed closure and disconnection.
The unit's reply could not deny the discharge, so it did not try. It set out the overload, the shift expansion, and a plan: an ETP upgrade designed on a treatability study, a trained operator, a sludge contract with an authorised TSDF, and an application for consent expansion. It applied for revocation once the upgrade was commissioned and outlet tests met norms. The board revoked closure with a bank guarantee and assessed environmental compensation counted from the date of the earlier inspection, because the unit had no records to show a later start. The upgrade cost far more than it would have two years earlier, and the missing records cost the most.
Mistakes factories make after an ETP failure
Keeping production running is the most expensive one. It feels like protecting the business, but it converts a repairable breakdown into a discharge case. The second is silence: hoping to fix the plant before anyone notices, without telling the board. If a complaint comes in meanwhile, the board sees concealment. The third is writing up the logbook afterwards. Inspectors and the NGT have seen enough backfilled logbooks to spot uniform handwriting and suspiciously perfect numbers.
The fourth is fixing the symptom and not the cause. Replacing a burnt blower when the real problem is overload means the next failure is weeks away. The fifth is treating the board's notice as a negotiation to be dragged out. Delay rarely helps, because the days of violation keep counting. And the sixth is ignoring the residents. A unit that meets the RWA or panchayat, explains what went wrong and what is being done, often avoids a tribunal case that would otherwise follow. For units already facing one, our guide on defending an NGT case filed against your industry sets out the approach.
An ETP compliance self-check
- Is the ETP sized for today's production and water use, not the figures in the original consent?
- Is there a trained operator on every shift that generates effluent?
- Do the inlet and outlet flow meters and the ETP electricity meter work, and are they read daily?
- Is the logbook filled in daily by the person who did the work?
- Is ETP sludge going to an authorised facility under a manifest?
- Does the consent allow any discharge at all, or is the unit on zero liquid discharge?
- Is there a written procedure for breakdowns, including informing the board?
- Are monthly outlet tests from a recognised laboratory on file?
Related guides
If your consent requires zero liquid discharge, read who must comply with ZLD and how boards check it. Units connected to a shared plant should read CETP compliance explained. Advocate B.K. Singh's advice to units after a failure is simple: write to the board before the board writes to you.
Frequently Asked Questions
Will the board close our factory if the ETP breaks down?
Not automatically. If you stop discharge, inform the board and repair quickly, closure is less likely; closure usually follows hidden breakdowns, bypasses or repeated failures.
Do we have to inform the pollution board about an ETP breakdown?
Many consent orders require it, and the EP Act places a duty to inform authorities of discharges above standards caused by accidents. Do it in writing and keep proof.
Can we keep running production while the ETP is repaired?
Only if effluent is stored or sent through an authorised route such as a CETP by tanker. Letting untreated effluent out to keep production going is a serious breach.
What is the penalty for a non-working ETP?
The board can order closure and disconnection and levy environmental compensation calculated per day of violation. Penalty proceedings under the amended Water Act are also possible.
How is environmental compensation for an ETP failure calculated?
By the CPCB formula, which multiplies factors including the industry category, days of violation, unit size and location. Good records limit the days counted.
Is ETP sludge hazardous waste?
For many industrial processes, yes. It needs authorisation, storage within limits, an authorised transporter with a manifest and disposal at an authorised facility.
Can we appeal a closure order passed over the ETP?
Yes. The NGT hears appeals against section 33A directions under section 33B; file within 30 days of receiving the order, or within a further 60 days if you can show sufficient cause.
How do we get electricity restored after disconnection?
Show the board the ETP is working, usually through a fresh inspection and sample, and apply for revocation. Boards often attach conditions such as a bank guarantee.
Our production has grown. Is our old ETP a problem?
Yes, if it is too small for present effluent. The board compares water use, production and treated volume, and expansion may also need fresh consent.
Can residents take us to the NGT over an ETP failure?
Yes. Affected residents can apply within 6 months of the cause of action, or within 5 years where they claim compensation for damage.
Are directors personally at risk?
The Water Act makes people in charge of a company's business answerable for its breaches in certain cases. After the 2024 amendment, much of this is handled through penalties, so take advice on the current position.
About the author
Advocate B.K. Singh, Founder & Principal Advocate, MCA, LL.B., LL.M.
Advocate B.K. Singh has practised for more than twenty years before the Supreme Court, the High Courts and the National Green Tribunal, and leads the environmental practice from offices in Dwarka (New Delhi) and Vaishali (Ghaziabad) with Advocate Sadhna Singh. Read his profile.
ETP failure, notice or closure?
Send us the board's notice or inspection report, your consent order and a short note on what failed and when, on WhatsApp or by phone.
This page gives general information about environmental law as it stood when it was last reviewed. It is not legal advice on your case and does not promise any result. Laws, rules, fees and time limits change, so check the current position for your matter before acting.
Have a question about your own case?
A guide can only go so far. Send us the notice, the order or a few photos, and we'll tell you where you stand, which authority or NGT bench deals with it and when the next step is due, in plain words.